Home Back

EVM Calculation Process

EVM Formulas:

\[ EV = \%\ complete \times BAC \] \[ PV = \%\ planned \times BAC \] \[ CV = EV - AC \] \[ SV = EV - PV \] \[ CPI = \frac{EV}{AC} \] \[ SPI = \frac{EV}{PV} \]

%
$
%
$

Unit Converter ▲

Unit Converter ▼

From: To:

1. What is Earned Value Management?

Earned Value Management (EVM) is a project management technique that integrates scope, schedule, and cost to measure project performance and progress. It provides quantitative data for project decision-making.

2. How Does the Calculator Work?

The calculator uses standard EVM formulas:

\[ EV = \%\ complete \times BAC \] \[ PV = \%\ planned \times BAC \] \[ CV = EV - AC \] \[ SV = EV - PV \] \[ CPI = \frac{EV}{AC} \] \[ SPI = \frac{EV}{PV} \]

Where:

3. Importance of EVM Metrics

Details: EVM metrics help project managers understand if the project is on budget (CV, CPI) and on schedule (SV, SPI). CPI > 1 indicates under budget, while SPI > 1 indicates ahead of schedule.

4. Using the Calculator

Tips: Enter percentage complete (0-100%), total project budget (BAC), percentage planned (0-100%), and actual costs incurred. All values must be positive numbers.

5. Frequently Asked Questions (FAQ)

Q1: What's the difference between EV and PV?
A: EV measures work actually completed, while PV measures work planned to be completed by a certain date.

Q2: What does a negative CV indicate?
A: A negative CV means the project is over budget (actual costs exceed earned value).

Q3: How is SPI interpreted?
A: SPI > 1 = ahead of schedule, SPI = 1 = on schedule, SPI < 1 = behind schedule.

Q4: When should EVM be used?
A: EVM is most valuable for projects with well-defined scope, schedule, and budget - typically in construction, IT, and engineering projects.

Q5: What are limitations of EVM?
A: EVM doesn't account for quality or technical performance, and requires accurate progress measurement to be effective.

EVM Calculation Process© - All Rights Reserved 2025